The new Air Force One has cost Boeing $3 billion and still isn't ready: the story of the VC-25B
Boeing agreed in 2018 to turn two 747-8s into the next Air Force One for a fixed price of $3.9 billion, to be finished by the end of 2024. The first is now due in mid-2028, and Boeing has recorded $3.17 billion in losses on the two airplanes, about 81 cents for every dollar of the price. This is the full story, with the documentary at the top: the deal, the hangar in San Antonio, the dates that kept moving, the used 747 from Qatar that carried the president first, and where Boeing's two jets came from.
Chapters in the video

Where the new Air Force One stands
As of late November 2026:
- Delivery: the first of Boeing's two VC-25Bs is due in the middle of 2028 and the second in the middle of 2029. The 2018 deal called for the job to be finished by the end of 2024.
- Price: the government agreed to pay about $3.9 billion for the two airplanes, at a fixed price.
- Boeing's losses: $3.171 billion through September 2026, all of it absorbed by Boeing.
- In the meantime: a used 747-8 that was built for Qatar's royal family first flew as Air Force One on July 1, 2026. It is an interim airplane.
- Still flying: the two 747-200s that have carried presidents since 1990.
The rest of this page is how it got here.
The jets flying today
For more than thirty-five years the president has flown on two Boeing 747-200s that the Air Force calls the VC-25A. The 747 beat the DC-10 for the job in the 1980s, and the first aircraft arrived in 1990. It was two years late, partly because of the complexity of installing the wiring for its communications gear.
Passenger 747-200s left the airlines years ago, which makes these two some of the last of their kind in the air. The Air Force One tracker on this site follows both by their transponder addresses and shows them whenever they broadcast a position.

What makes a presidential 747 hard to build
Wiring is a large part of it. Each VC-25A carries about 238 miles of wiring, roughly twice what an airline 747 has, and it is hardened against the electromagnetic pulse from a nuclear blast. The airplane has a medical suite that can work as an operating room and 85 telephones, and it can take on fuel in flight from a tanker.
In January 2015 the Air Force picked the replacement: Boeing's newest and largest jumbo, the 747-8. There was no competition. Airbus's parent company had decided years earlier that it wouldn't bid.
Boeing had the job to itself. The open question was what it would charge.

"Cancel order"
On December 6, 2016, six weeks before he took office, President-elect Donald Trump raised that question on Twitter. He wrote that the costs of the new Air Force One were out of control, at more than $4 billion, and he ended with two words: "Cancel order!"
At that point Boeing held a contract worth $170 million to work out what the new airplanes would need. The Air Force had budgeted $2.7 billion for development. Nobody said where the $4 billion figure came from.
Boeing's chief executive, Dennis Muilenburg, met with Trump twice in the next six weeks. In 2017 the White House dropped one requirement to save money: the new jets won't be able to refuel in flight, which the current ones can.
On February 27, 2018, the White House announced a deal: $3.9 billion for two airplanes, at a fixed price. The White House said it would save taxpayers more than $1.4 billion. Boeing said the president had negotiated a good deal on behalf of the American people.
The fixed price is why this became Boeing's problem. The government agreed to pay about $3.9 billion, a figure that later changes to the contract have raised. Whatever the work cost beyond the price would come out of Boeing. The job was to be finished by the end of 2024.
Boeing had a reason to think it could be done. The two airplanes already existed, and the Air Force had bought them the previous August.
The hangar in San Antonio
The two 747s went to a Boeing hangar in San Antonio, Texas. Work on the first started in February 2020 and on the second that June. The job was to open up two finished airliners and rebuild them as flying command posts.
The trouble started with the interiors. Boeing had hired a Texas company, GDC Technics, to design and build them. In April 2021 Boeing sued, said the supplier was about a year behind, and canceled the contracts. GDC sued back on April 16, blaming Boeing, and filed for Chapter 11 bankruptcy on April 26.
Then there was the workforce. The program has strict security requirements, and the Government Accountability Office reported in 2022 that fewer skilled workers were getting clearances than Boeing had planned.
The Wall Street Journal reported two more problems from the hangar. Workers had put one of the jets on jacks, and the load on some of them went over the limit; the Air Force said the airplane wasn't damaged. And two empty miniature tequila bottles turned up inside one of the aircraft.
The cost landed on Boeing's books. It recorded a loss of $168 million on the program in 2020 and $318 million in 2021. On April 27, 2022, it added $660 million for a single quarter, which took the total past $1.1 billion. That day Boeing's chief executive, Dave Calhoun, said the deal carried "a very unique set of risks that Boeing probably shouldn't have taken."
The date keeps moving
The first date to go was 2024. In 2022 the Air Force said the jets would be two to three years late, and the new schedule put the first delivery in 2027. In February 2024 Boeing told the Air Force it would be December 2029.
In 2025 the two sides pulled that back. The current target is the middle of 2028 for the first airplane and the middle of 2029 for the second.
Air Force officials told the GAO what was behind it: design problems that kept coming, rework on modifications that were already done, and a shortage of workers. The wiring was part of it again. In March 2022 Boeing stopped making wiring for the jets after it found what the auditors called "a large number of unexpected design errors."
Boeing and the Air Force also moved the certification of the airplane from the FAA to the Air Force itself, a change the GAO described as shifting risk to the government. By October 2025, seven of the 80 certification plans had been approved.
The airframes brought a problem of their own. Bloomberg reported in August 2026 that the Air Force had counted about 300 cracks in the stringers of each jet, the long stiffeners that run along the inside of an aircraft's skin. Stress corrosion cracking is a known problem on the 747-8, and Boeing is repairing it.
What it has cost Boeing: $3.17 billion so far
The losses kept coming. Boeing's annual and quarterly reports to the Securities and Exchange Commission put its charges on the program at:
- 2020: $168 million
- 2021: $318 million
- 2022: $1.452 billion, including the $660 million first quarter
- 2023: $482 million
- 2024: $379 million
- 2025: $60 million
- 2026, January to September: $312 million, of which $280 million came in the second quarter
That is $3.171 billion, about 81 cents lost for every dollar of the $3.9 billion price Boeing agreed to in 2018. The total passed $3 billion with the results Boeing published on July 28, 2026.
On October 16, 2026, Boeing and the Air Force signed new contract terms to match the new schedule. Boeing told investors that it "may record additional losses in future periods."
It is not the only Boeing program to run years late; the story of the 787 Dreamliner is on this site too.
The third 747
Donald Trump returned to the White House in January 2025, and the airplanes he had negotiated in 2018 were years overdue. He found another 747.
In February 2025 Trump toured a 747-8 parked at Palm Beach International Airport. Boeing had delivered it in 2012 as a private jet for Qatar's royal family. In May 2025 the Defense Department accepted that airplane from Qatar as a gift.
The gift was disputed from the first day. Democratic lawmakers argued that accepting a jet from a foreign government without the consent of Congress violates the Constitution's limit on foreign gifts, and several conservative commentators criticized it too. The administration's position is that the gift is legal because it was made to the United States government, and that the airplane will pass to Trump's presidential library foundation before he leaves office. This page reports both positions and takes neither.
The contractor L3Harris converted the jet in Texas. Work began in September 2025, and on May 1, 2026, the Air Force announced that the modification and the flight testing were done. The Air Force secretary had said the work would probably cost less than $400 million; the details are classified. The Air Force calls the airplane the VC-25B Bridge.
On July 1, 2026, it flew as Air Force One for the first time, to Bismarck, North Dakota.
It is an interim airplane. The Air Force says that "no risk was taken in security, safety, or mission communications," and that it made trades on "some of the less commonly used mission sets." Eighteen days after that first trip, the president said the jet would go back in to be, in his words, "maxed out." It was flying again by November, when it brought him home from China without stopping.
A used 747 was converted in less than a year. Boeing's two have been in the hangar for more than six. Part of that gap is the job: Boeing's jets are being built to the full specification, and the interim jet's exact configuration is classified.

Who they were built for
Boeing's two jets have a history of their own. Neither was built for the White House. They came from a Russian airline's order.
In 2013 Transaero, then Russia's second-largest airline, signed up for four 747-8s. Boeing built two of them. Then Transaero collapsed in 2015, and it never took them. Aeroflot absorbed most of the failed airline's fleet. It turned the jumbos down.
Boeing was left with two new 747s that no airline wanted. In February 2017 it flew them to Victorville, in California's Mojave Desert, where the hot, dry air holds off corrosion, and it paid to keep them there while it looked for a buyer.
That August the Air Force bought them. A new 747-8 listed for about $387 million. Neither side said what the Air Force paid. Officials said the military was getting a good deal.
Those are the airplanes Boeing agreed to turn into Air Force One for a fixed price. They were built for a Russian airline that collapsed, and they were parked in the desert when the Air Force bought them. What it paid has never been published. Boeing's losses on converting them have passed $3 billion.

Boeing had been here before
The contract for the Air Force One jets flying today, signed in 1986, was a fixed price too: a little over $250 million for two airplanes. Those jets were the ones that arrived two years late. By 1989 the Air Force estimated that Boeing was $385 million over budget, and under the contract Boeing had to absorb it.
The last 747s Boeing will deliver
There is one more number. Boeing built 1,574 747s. The last one off the line was a freighter, and it went to Atlas Air on January 31, 2023. That airplane, N863GT, has its own page here.
The two jets in San Antonio were built years before that one. When Boeing hands them over, they will almost certainly be the last 747s it ever delivers, more than a decade after they were built.
Until then, the Air Force One tracker shows the two VC-25As and the interim 747-8 whenever they broadcast a position, which the presidential fleet often doesn't; how ADS-B tracking works explains what a tracker can and can't see. The vice president's jets are on the Air Force Two tracker, and the E-4B command posts, which are 747-200s as well, are on the doomsday plane tracker. Every other 747 that is still flying is on the live 747 tracker.

Timeline: the new Air Force One, 2015 to 2026
- January 2015: the Air Force picks the 747-8, with no competing bid.
- December 6, 2016: the "Cancel order!" tweet.
- February 2017: Boeing flies the two undelivered Transaero 747-8s to storage at Victorville.
- August 2017: the Air Force buys them for a price that has never been published.
- February 27, 2018: the fixed-price deal, $3.9 billion for two airplanes, to be finished by the end of 2024.
- February and June 2020: conversion work starts in San Antonio.
- April 2021: Boeing and its interiors supplier sue each other, and the supplier files for bankruptcy.
- March 2022: Boeing stops making wiring for the jets over design errors.
- April 27, 2022: a $660 million quarterly loss, and the chief executive's remark about the deal.
- February 2024: Boeing's delivery estimate reaches December 2029.
- May 2025: the Defense Department accepts a 747-8 from Qatar.
- 2025: the schedule is pulled back to mid-2028 and mid-2029.
- July 1, 2026: the interim 747-8 flies as Air Force One for the first time.
- July 28, 2026: Boeing's losses on its two jets pass $3 billion.
- October 16, 2026: Boeing and the Air Force sign new contract terms.
Questions
When will the new Air Force One be ready?
The current target is the middle of 2028 for the first of Boeing's two VC-25Bs and the middle of 2029 for the second. The 2018 deal called for the job to be finished by the end of 2024. In February 2024 Boeing's estimate had slipped to December 2029, and Boeing and the Air Force pulled it back in 2025.
How much does the new Air Force One cost?
In February 2018 the government agreed to pay Boeing a fixed price of about $3.9 billion for two airplanes, a figure that later changes to the contract have raised. Costs above the price fall on Boeing, which has recorded $3.171 billion in losses on the program through September 2026, about 81 cents for every dollar of the 2018 price.
Why is the new Air Force One so late?
Air Force officials told government auditors it came down to design problems that kept coming, rework on modifications already done, and a shortage of workers. Boeing said its interiors supplier was about a year behind before the two sued each other in 2021, Boeing stopped making wiring in March 2022 over design errors, and the airframes need repairs for stress corrosion cracking.
What is the VC-25B?
VC-25B is the Air Force's name for the next presidential aircraft: two Boeing 747-8s being converted in San Antonio, Texas, to replace the two VC-25As, the 747-200s that have flown presidents since 1990. The used 747-8 from Qatar that first flew as Air Force One in July 2026 is called the VC-25B Bridge, an interim airplane.
Is the 747 from Qatar the new Air Force One?
It flies as Air Force One, but as an interim airplane. The Defense Department accepted the 747-8 from Qatar as a gift in May 2025, L3Harris converted it in Texas, and it first carried the president on July 1, 2026. The permanent replacements are Boeing's two VC-25Bs, now due in mid-2028 and mid-2029.
Where did the two new Air Force One 747s come from?
They were built for Transaero, a Russian airline that ordered four 747-8s in 2013 and collapsed in 2015 before taking any. Boeing flew the two finished jets to desert storage at Victorville, California, in February 2017, and the Air Force bought them that August. What it paid has never been published.
Can the new Air Force One refuel in flight?
No. In 2017 the White House dropped in-flight refueling from the requirements to save money, so Boeing's two VC-25Bs will not be able to take on fuel from a tanker in flight. The VC-25As flying today can.
Sources
- Boeing's losses, the contract reset of October 16, 2026 and the "additional losses" warning: Boeing annual and quarterly reports to the SEC, 2020 to 2026, and Boeing's results release of July 28, 2026
- Schedule, security clearances, wiring, certification and stress corrosion cracking: U.S. Government Accountability Office, Weapon Systems Annual Assessments, 2022 to 2026
- The 2016 tweet and the 2018 deal: Boeing statement of December 6, 2016; White House and Boeing statements of February 27, 2018
- In-flight refueling dropped in 2017: Gen. Joseph Dunford, Senate Armed Services Committee, September 26, 2017
- GDC Technics: CNBC, April 2021. The chief executive on the deal: CNBC, April 27, 2022
- The hangar incidents: The Wall Street Journal, via Reuters, April 2022
- The stringer cracks: Bloomberg, August 20, 2026, citing the Air Force
- The Transaero airframes: Defense One, August 1, 2017
- The interim 747-8: Air & Space Forces Magazine and The War Zone, 2025 to 2026; U.S. Air Force statements
- The 1986 contract for the current Air Force One: HistoryLink essay 21244
- The last 747: Boeing, January 31, 2023
More stories
- The $30 billion bet that nearly broke Boeing: the story of the 787 Dreamliner
- The four-engine jet Lufthansa couldn't retire: the story of the A340
- The airliner that outlived its maker: the story of the MD-11