The New Air Force One Has Cost Boeing $3 Billion. It's Still Not Ready.

10 min 50 s · published November 23, 2026 · Watch on YouTube

Boeing agreed in 2018 to turn two 747-8s into the next Air Force One for a fixed price of $3.9 billion, to be finished by the end of 2024. The first is now due in mid-2028, and Boeing has recorded $3.17 billion in losses on the two airplanes, about 81 cents for every dollar of the price. This is the full story, with the documentary at the top: the deal, the hangar in San Antonio, the dates that kept moving, the used 747 from Qatar that carried the president first, and where Boeing's two jets came from.

Written and maintained by Jacob McEwen, M.S. Electrical Engineering·Last updated

Chapters

  1. 0:00 $3 billion lost, still not ready
  2. 0:21 What Air Force One has to do
  3. 1:29 "Cancel order"
  4. 2:56 The hangar in San Antonio
  5. 4:38 The date keeps moving
  6. 6:33 The third 747
  7. 8:24 Who they were built for
  8. 9:32 Boeing had been here before

Background: Where the new Air Force One stands

As of late November 2026:

  • Delivery: the first of Boeing's two VC-25Bs is due in the middle of 2028 and the second in the middle of 2029. The 2018 deal called for the job to be finished by the end of 2024.
  • Price: the government agreed to pay about $3.9 billion for the two airplanes, at a fixed price.
  • Boeing's losses: $3.171 billion through September 2026, all of it absorbed by Boeing.
  • In the meantime: a used 747-8 that was built for Qatar's royal family first flew as Air Force One on July 1, 2026. It is an interim airplane.
  • Still flying: the two 747-200s that have carried presidents since 1990.

The rest of this page is how it got here.

Continued in the written story, with 11 more sections, photos and sources.

Read the full story

The written version, with photos and every source: The new Air Force One has cost Boeing $3 billion and still isn't ready: the story of the VC-25B